Work Center Capacity

The theoretical Production Work Center Capacity is calculated as follows:

  • number of resources available - standard Odoo field
  • efficienty factor - standard Odoo field
  • working days per week
  • working hours per days
  • number of shifts per day

This is reported into workorders for information purposes.

The theoretical Production Work Center Capacity is used to consolidate "Master Production Plan" performing "Rough Capacity Check".

Please log in to comment on this module

  • The author can leave a single reply to each comment.
  • This section is meant to ask simple questions or leave a rating. Every report of a problem experienced while using the module should be addressed to the author directly (refer to the following point).
  • If you want to start a discussion with the author, please use the developer contact information. They can usually be found in the description.
Please choose a rating from 1 to 5 for this module.
have a nice day
by
kkhalidabed@gmail.com
on 7/7/20, 5:00 PM

my question is how to calculate sales for many work centers producing the same product without configuring the alternative work center

Re: have a nice day
by
claudio candito
on 7/8/20, 12:33 AM Author

Please write us to info@openvalue.cloud


There are no comments yet!